Engineered Spray Solutions LLC, (ESS) will be cleaning and rehabilitating sanitary sewer manholes in your area. Every effort will be made to complete this work with minimum impact to the resident and traffic flow through the work area.
ESS is scheduled to begin cleaning and rehabilitation activities on 8/28/23 and is anticipated to be completed by 9/1/23. Activities will occur between the hours of 7:00am and 5:00pm.
Anticipated Schedule:
8/28/2023 MH C2-10 N Church St and E Woodland St
8/28/2023 MH A1-7A Dr. Carter Blvd
8/29/2023 MH D8-16 South Stone Street / W. Court Ave
8/29/2023 MH D9-60 Elm Ave /S Forsyth Ln
8/30/2023 MH A1-39 410 S Anderson St
8/30/2023 MH 61 Palm Dr b/w 1st & 2nd Ct
8/31/2023 MH 65 Palm Dr b/w 2nd and 3rd CT
8/31/2023 MH 62 Palm Dr b/w 3rd & 4th CT
9/01/2023 MH 64 behind 31 Palm Dr
9/01/2023 MH 63 behind 33 Pelican Dr
If lane closures are necessary during this work, please drive slowly and observe construction/traffic signs and flaggers.
PLEASE DO NOT PARK VEHICLES ON TOP OF MANHOLE COVERS
Please remove any personal items within the road/street right-of-way work area. Please note that any damages we cause to your property will be returned to equal condition (sod, sprinklers, pavers, etc.) Your tolerance and support are greatly appreciated to achieve our goal of improving your neighborhood and manhole integrity.
Should you have any questions or concerns, feel free to contact the City of Bunnell, Infrastructure Department at (386) 437-7500.